Points to be verified whilst foundation work is underway and prior to paying subcontractors
- Check that you have all of your building materials
- Check that boundary markings are in place
- Locate the tradesmen’s entrance and make sure that it is located in the position indicated on the work plan
- Check the positioning of footing against the plan
- Check the width of the footing (24” or 30” in accordance with the plan)
- Check the flange measurements (dimensions in length as per the plan)
- Check the 3 rebars parallel at 4'' from the ground
- Check concrete flow
- Check the installation of the drain tile stuck to flanges
- Check the installation of the drain tile
- Check the spread of gravel DB (drain tile and & subfloor)
- Check the surveyor’s work (positioning of the nails in the flanges)
- Check the installation of the geotextile membrane if requested
- Check the key in the exterior wall flange
- Measure distances using a measuring tape
- Check that the formworker has been provided with the correct specifications
- Check the installation of the foundation or box windows (2*8 or 2*10)
- Check wall widths (10” or 8” in accordance with plan)
- Check wall heights (balcony + ground floor + garage + pillars)
- Check positioning of openings for ducts (sleeves)
- Check positioning of rebars (2 bars 15m at the top - bottom + top of windows)
- Check concrete flow
- Check breakage of formwork tie rods
- Check the plastered formwork tie rods
The excavation work forms the foundation of the entire house!